South32

GEMCO Shipload Feed Conveyor Replacement

Project Summary

Wave International (Wave) was engaged to revitalise the integrity of a shipload feed conveyor located in Northern Territory, Australia. The initiative aimed to ensure longevity and efficiency in operations. The client expected a detailed conditional assessment report including remediation options. The assessment report indicated that 370 meters of the conveyor structure required a replacement. Wave then developed several innovative concept design options aimed at replacing the conveyor modules with minimal production impact. After the client approved the preferred design option, Wave moved forward with the detailed design and also aided in formulating the construction Statement of Work (SOW).